Meaning of contract target cost (ctc)

 

 

 

Contract Target Cost (CTC)

 

The following texts are the property of their respective authors and we thank them for giving us the opportunity to share for free to students, teachers and users of the Web their texts will used only for illustrative educational and scientific purposes only.

 

The information of medicine and health contained in the site are of a general nature and purpose which is purely informative and for this reason may not replace in any case, the council of a doctor or a qualified entity legally to the profession.

 

Business project management glossary

 

Meaning of term contract target cost (ctc) :

 

The negotiated costs for the original definitized contract and all contractual changes that have been definitized, but excluding the estimated cost of any authorized, unpriced changes. The CTC equals the value of the BAC plus management or contingency reserve.

 

The meaning indicated above are indicative not be used for legal purposes

Source : http://files.perevedem.ru/Glossaries/Project%20management/big-group%20(Business%20project%20management%20glossary).doc

 

Google key word : contract target cost (ctc)

Author : not indicated on the source document of the above text

If you are the author of the text above and you not agree to share your knowledge for teaching, research, scholarship (for fair use as indicated in the United States copyrigh low) please send us an e-mail and we will remove your text quickly.

 

Contract Target Cost (CTC)

 

If you want to quickly find the pages about a particular topic as contract target cost (ctc) use the following search engine:

 

 

Meaning of term contract target cost (ctc)

 

Please visit our home page

 

Larapedia.com Terms of service and privacy page

 

 

 

Meaning of term contract target cost (ctc)